We take a developer or designer's furniture and furnishings specification and turn it into a delivered package: manufacturability review, shop drawings, sampling, production, dry assembly, export packing and site delivery. One contract, one programme, one invoice.

How an FF&E commission runs
- 01
Specification review
We read the designer's schedule and flag anything that cannot be produced as drawn, with an alternative.
- 02
Sample approval
A physical sample box — veneer, metal, stone and upholstery — approved before any production.
- 03
Shop drawings
Item-level drawings and a finish schedule, signed off against the design intent.
- 04
Manufacture & dry assembly
Production, then every piece assembled and photographed before packing.
- 05
Delivery & installation
Consolidated shipping, room-number labelling, and installation sequencing with your site contractor.
What we can supply
| Category | Typical items | Lead time |
|---|---|---|
| Seating | Sofas, armchairs, lounge chairs, benches, stools | 45 – 60 days |
| Tables | Dining, coffee, console, side tables | 40 – 60 days |
| Case goods | Sideboards, cabinets, nightstands, chests | 50 – 70 days |
| Bedroom | Beds, headboards, dressing tables, mirrors | 45 – 70 days |
| Fixed millwork | Wall panels, wardrobes, libraries, islands | 75 – 120 days |
| Soft furnishing | Curtains, rugs, cushions, throws, art | 30 – 45 days |
| Outdoor | Teak sets, daybeds, parasols, planters | 50 – 80 days |
| Accessories | Tableware, decorative objects, bathroom accessories | 25 – 40 days |

A manufacturability review saves months
The most expensive FF&E problems are found on site, not in the drawings. A 12mm radius that no factory can produce, a veneer sheet that does not exist in the length required, an upholstery specification that will not pass a fire test for a hotel use. We run a manufacturability review before anything is quoted, so the programme does not absorb those discoveries in month three.
- Dimension, material and finish checked against actual production capability
- Fire, abrasion and material certifications confirmed for the destination use
- Lead times flagged for every item before the programme is committed
- Substitutions proposed with the same visual intent, not a downgrade
Send us the specification
We will review it, flag anything we cannot make, and price the rest.